ClarWorks

Behind the model

How the solar model works

Every number in the calculator is derived bottom-up from your inputs — no black box. Below is each formula, paired with a worked example from the default 1 MWp factory-rooftop plant at 16% CUF, saving an avoided grid tariff of 8/kWh. Change any input in the tool and these relationships hold.

Capacity, CUF & generation

Nameplate capacity and the capacity-utilization factor (CUF) set first-year output. The plant runs at full output from commissioning (no ramp); panel degradation erodes output each subsequent year.

Year-1 generation

MWp × CUF% × 8760 h × 1000

1 × 16% × 8760 × 1000 = 1,402 MWh

Specific yield

CUF% × 8760 (kWh per kWp)

1,402 kWh/kWp

Degradation (compounding)

gen × (1 − degradation%)^(age−1)

yr 2 = 1,395 MWh (−0.5%/yr)

Lifetime generation

Σ annual generation over the horizon

33,016 MWh over 25 yrs

CapEx — build cost

Module-and-BoS cost per Wp drives the EPC; land, evacuation/grid lines and contingency stack on top, then interest-during-construction is capitalized. Cost per Wp is an output, never an assumption when you edit components.

EPC

MWp × 1,000,000 Wp × cost/Wp

1M Wp × ₹38 = ₹3.8 Cr

Line items (evacuation, approvals…)

Σ line items (unit cost × qty)

₹3 L

Base cost

EPC + land + lines

₹3.8 Cr + ₹0 + ₹3 L = ₹3.83 Cr

Contingency

base × 3%

₹11.5 L

Interest during construction (IDC)

total × debt% × interest% × (months ÷ 12) × ½

3 mo → ₹3.62 L

Total project cost

base + contingency + IDC

₹3.98 Cr

CapEx per Wp (derived)

total project cost ÷ (MWp × 1e6)

₹39.81/Wp

OpEx — annual running cost

O&M scales with online capacity; insurance is a % of CapEx; land lease is fixed. All escalate each year.

O&M

online MWp × ₹6,00,000/MWp × (1+4%)^(yr−1)

yr 1: ₹6 L

Insurance

base CapEx × 0.25% × (1+esc)^(yr−1)

yr 1: ₹98,623

Land lease

₹0 × (1+esc)^(yr−1)

yr 1: ₹0

Total OpEx

O&M + insurance + land lease

yr 1: ₹6.99 L

Revenue — tariff or savings rate

Revenue is generation × the tariff/savings rate, escalated each year. The rate carries three Indian segments: a PPA sale price (utility auctions ₹2.5–2.6/kWh), the avoided grid tariff for captive/rooftop plants (₹7–9 commercial), or the grid tariff net of ₹1.5–2.5 open-access charges for third-party supply. Phased builds bring MWp online over time, each cohort on its own degradation clock.

Revenue / savings

generation × tariff/savings rate × (1 + esc%)^(yr−1)

yr 1: 1,402 MWh × ₹8 = ₹1.12 Cr

Escalation

rate × (1 + 3%)^(yr−1)

3%/yr (grid tariffs drift up)

Phased build (vintages)

each phase commissions on its own year, capex & debt timed to commissioning

all-at-once by default

Financing — debt, moratorium, tax & depreciation

Long-tenor project debt with an interest-only moratorium during commissioning, then the principal amortizes over the remaining tenor. Depreciation defaults to the Indian Sec 32 accelerated schedule (40% written-down value) — the tax lever behind C&I solar — with a straight-line book option. Land is excluded from the depreciable base in both methods. Tax carries losses forward.

Debt / equity split

debt = total cost × debt% ; equity = remainder

₹2.79 Cr debt · ₹1.19 Cr equity (70/30)

Principal moratorium

interest-only for the first N years from commissioning, then amortize

1 yr grace, 10 yr tenor

Equal-principal repayment

debt ÷ (tenor − moratorium) each amortizing year

₹31 L

Annuity (EMI) option

debt × r ÷ (1 − (1+r)^−(tenor−moratorium))

level-payment alternative

Interest

outstanding balance × interest rate

yr 1: ₹29.3 L

Depreciable base (land excluded)

total project cost − land

₹3.98 Cr

Depreciation — 40% WDV (Sec 32)

base × 40% × 60%^(yr−1) (declining balance)

yr 1: ₹1.59 Cr · yr 2: ₹95.5 L

Depreciation — straight-line option

base ÷ 15 yrs

₹26.5 L/yr for 15 yrs

Tax (with loss carryforward)

max(0, PBT − losses) × 25% ; losses carry forward

accelerated depreciation shelters early-year profit

Returns & coverage

The unlevered cash flows give the project view; the equity cash flows give the geared view. Project IRR uses a separate project tax that excludes the interest shield, so it is genuinely financing-independent. Construction beyond a year defers first revenue.

EBITDA

revenue − operating cost

yr 1: ₹1.05 Cr (94% margin)

Unlevered (project) FCF

EBITDA − project tax − CapEx (project tax excludes interest)

Project IRR 25.4%

Equity FCF

PAT + depreciation − principal − equity-funded CapEx

Equity IRR 50.9%

NPV

Σ unlevered FCF ÷ (1 + discount)^t

@ 10% = ₹5.42 Cr

Construction lead

ceil(months ÷ 12) − 1 extra zero-revenue years before generation

none (3 mo ≤ 12)

Payback

year cumulative unlevered cash flow first turns positive

3.8 yr

DSCR

CFADS ÷ debt service ; CFADS = EBITDA − tax (amortizing years only)

min 1.79× · avg 2.21× (yr 2 = 1.79×)

LLCR

PV(CFADS over loan life) ÷ debt

2.23×

Equity multiple (MOIC)

Σ equity cash returned ÷ equity invested

19.57×

Break-even tariff

tariff at which project NPV = 0

₹3.45/kWh

LCOE & ESG

The levelized cost of energy — discounted, so it is directly comparable to a PPA tariff or your grid rate — and what the plant displaces on the grid.

LCOE (discounted)

(capex + PV of OpEx) ÷ PV of generation, at the 10% discount rate

₹3.96/kWh (vs ₹8 tariff/savings rate)

Carbon avoided (annual)

year-1 generation × grid emission factor ÷ 1000

995 tCO₂/yr

Carbon avoided (lifetime)

Σ generation × grid emission factor ÷ 1000

23,441 tCO₂

Land footprint

MWp × 2 acres/MWp

2 acres

These are transparent planning estimates, not a quote. A real solar project needs a proper feasibility study, resource assessment and DPR — that’s where we help. Open the calculator →