Behind the model
How the data center model works
Every number in the calculator is derived bottom-up from your inputs — no black box. Below is each formula, paired with a worked example from the default 10 MW Tier III colocation build. Change any input in the tool and these relationships hold.
Sizing
Total IT load is the sum of the build phases (capacity is defined by the schedule, not a standalone input). The intensity and land inputs then derive the hall count, rack count and the auto-sized critical equipment (with tier redundancy).
Total IT load
Σ phase MW (the single capacity input)
10 = 10 MW
Data halls
⌈ IT load ÷ MW per hall ⌉
⌈ 10 ÷ 2 ⌉ = 5
Total racks
⌊ IT load × 1000 ÷ rack kW ⌋
⌊ 10000 ÷ 8 ⌋ = 1,250
Facility power
IT load × PUE
10 × 1.5 = 15.0 MW
Equipment count (Tier III = N+1)
⌈ served load ÷ unit rating ⌉ + 1 spare
DG: ⌈ 15 ÷ 2 ⌉+1 = 9; UPS: 21
Per-phase sizing & pooled redundancy
each phase's base units are sized from its own MW; the redundancy spare is added once (with phase 1) and shared across the facility, not repeated per phase
a 5+5 MW build keeps the same 9 DG sets as a one-shot 10 MW build
System sub-total
Σ (unit count × unit cost), all four systems
₹85.8 Cr
CapEx — build cost
Auto-sized systems + shared infra (once) + per-hall infra (× halls), then contingency and interest-during-construction. Every line carries a function, so the same numbers roll up into a clean MECE taxonomy that also drives depreciation and maintenance. Per-MW is an output, never an assumption.
Shared / core infra (×1)
Σ shared line items
₹89.8 Cr
Per-hall infra (× halls)
Σ per-hall items × hall count
₹38.5 Cr × 5 = ₹193 Cr
By function (MECE)
every line classified into Land / Building / Power / Cooling / IT / Security / Soft
Land ₹31.8 Cr · Building & civil ₹132 Cr · Power & electrical ₹128 Cr · Cooling & mechanical ₹33 Cr · IT / white-space ₹20 Cr · Security & BMS ₹10 Cr · Soft costs ₹13 Cr
Sub-total
systems + shared + per-hall
₹368 Cr
Contingency
sub-total × 8%
₹29.4 Cr
Interest during construction (IDC)
total × debt% × interest% × (months ÷ 12) × ½
18 mo → ₹17.9 Cr
Total project cost
sub-total + contingency + IDC
₹415 Cr
Cost timing (upfront vs phased)
upfront = built once with phase 1 (land, grid, design…); phased = drawn pro-rata as each phase commissions. Contingency + IDC are allocated so upfront + phased = total.
₹101 Cr upfront + ₹314 Cr phased = ₹415 Cr
Construction-cost escalation
each phase's phased capex × (1 + 5%)^(build year). Phase 1 (year 0) is unescalated, so a single-phase build is unaffected; staging later raises the as-built total.
5%/yr
Land (Own vs Lease)
owned land sits in CapEx; leased land is dropped from CapEx and recovered as an annual OpEx
owned — ₹31.8 Cr in CapEx
Stamp duty on land
land value × 6% — owned land only, capitalized into the land basis (never depreciated, insured or maintained). 5–7% by state; UP/TN data-center policies waive it.
₹1.8 Cr
GST (planning note, not a model line)
18% GST applies on equipment and construction services; input tax credit on the civil shell is blocked u/s 17(5) CGST — budget unrecoverable GST on the building share as cost
enter cost lines GST-adjusted
CapEx per MW (derived)
total project cost ÷ IT load
₹41.5 Cr / MW
OpEx — annual running cost
Energy scales with online capacity and occupancy (with a part-load PUE option); maintenance is split by asset class on the depreciable base, insurance is on the installed base excluding land; genset fuel and (when land is leased) land lease are explicit lines; fixed lines escalate each year.
Facility power drawn
IT × occ + (PUE−1) × IT × (fixedOH + (1−fixedOH) × occ)
year 1: 6.0 MW
Energy cost
facility power × 8760 h × tariff × 1000 × (1+esc)^(yr−1)
stabilized: ₹98.3 Cr/yr
Power pass-through (revenue)
when pass-through is on, energy is billed back on the revenue side (margin-neutral)
recovered ₹98.3 Cr/yr
Generator fuel
facility power × test hours × 1000 × 0.27 L/kWh × diesel price × (1+esc)^(yr−1)
year 1: ₹1.9 Cr/yr
Maintenance (split by class)
building base × 1% + equipment base × 3% (land excluded)
₹9.7 Cr/yr (escalated)
Insurance (excl. land)
installed base excl. land × 0.35% / yr
₹1.55 Cr/yr
Upkeep only on commissioned assets
in a staged build, maintenance, insurance and genset-test fuel scale with the commissioned share of the as-built cost — phases not yet built carry no upkeep
single build: full base from year 1
Land lease (lease tenure only)
land value × 8% / yr — only when land is leased
owned → 0 (land in CapEx)
Fixed lines escalate
base × (1 + 5%)^(yr−1)
staff, connectivity, property tax
Revenue
A single power-exclusive rate per kW of occupied IT power — the space + cooling + service fee. Tenant power is recovered separately via the pass-through toggle. Capacity, occupancy and lease-up all live in the build schedule — total IT load is the sum of the phase MW; a single phase is the complete one-time project; add phases to stage the build.
Rent revenue
occupied IT kW × rate/kW/mo (₹7,200) × 12 × (1+esc)^(yr−1) + (pass-through ? energy : 0)
stabilized: ₹188 Cr/yr
Power pass-through
pass-through on → tenant energy billed on top of the rate; off → operator absorbs energy as a cost
on — recovered ₹98.3 Cr/yr
Occupancy ramp (per phase, linear)
start + (stabilized − start) × (age−1) ÷ (ramp yrs − 1)
40% → 95% over 4 yrs (default phase)
Phase commissioning (fixed year vs fill-triggered)
phase 1 commissions on its online year; a later phase either pins a fixed year or commissions when the PRIOR phase hits its fill threshold, plus a build lag
fill 70% + 1-yr lag (default for added phases)
Single-source phasing
phases are the only schedule — capacity = Σ phase MW; each phase draws capex the year before online and leases up on its own ramp; shared/upfront cost is carried by the first phase
shared infra carried by phase 1
Financing — debt, tax & depreciation
Long-tenor infrastructure debt with an interest-only moratorium during lease-up, straight-line split depreciation, and tax with loss carryforward.
Debt / equity split
debt = total cost × debt% ; equity = remainder
₹249 Cr debt · ₹166 Cr equity
Principal moratorium
interest-only for the first N years from first online, then amortize
3 yr grace, 12 yr tenor
Equal-principal repayment
debt ÷ (tenor − moratorium) each amortizing year
₹27.7 Cr
Annuity (EMI) option
debt × r ÷ (1 − (1+r)^−(tenor−moratorium))
level payment alternative
Interest
outstanding balance × interest rate
year 1: ₹24.9 Cr
Depreciation (straight-line, by class)
building-class base ÷ building life + equipment-class base ÷ equipment life (from the CapEx functional categories; land excluded, soft/contingency/IDC allocated pro-rata)
30-yr building · 12-yr equipment
Tax (with loss carryforward)
max(0, PBT − losses) × 25% ; losses carry forward
shelters early-year losses
Returns & coverage
The unlevered cash flows give the project view; the equity cash flows give the geared view. Project IRR excludes the interest shield so it is financing-independent.
EBITDA
revenue − operating cost
stabilized: ₹68.1 Cr (36% margin)
Unlevered (project) FCF
EBITDA − project tax − CapEx (project tax excludes interest)
Project IRR 13.9%
Equity FCF
PAT + depreciation − principal − equity-funded CapEx
Equity IRR 18.9%
NPV
Σ unlevered FCF ÷ (1 + discount)^t
@ 11% = ₹105 Cr
Payback
year cumulative unlevered cash flow first turns positive
9.4 yr
DSCR
CFADS ÷ debt service ; CFADS = EBITDA − tax (amortizing years only)
min 1.29× · avg 1.53×
LLCR
PV(CFADS over loan life) ÷ debt
1.30×
Equity multiple (MOIC)
Σ equity cash returned ÷ equity invested
5.83×
Terminal value at exit
exit multiple × final-year EBITDA (− capital-gains tax)
₹939 Cr
Break-even occupancy
stabilized occupancy at which NPV = 0
80%
Operations & ESG
What the facility consumes and emits at the stabilized run-rate, plus the physical capacity ceiling.
Effective PUE
facility power ÷ IT power (≥ design PUE when overhead is fixed)
1.50
Design availability (by tier)
Uptime Institute target; downtime = (1 − uptime) × 525,600 min
Tier III: 99.982% → 1.6 h/yr
Carbon
grid energy (net of renewables) × grid factor + diesel test energy × diesel factor
89,163 tCO₂e/yr
Water
WUE × IT energy
149.8 ML/yr
Binding constraint
min( racks by power, by white-space, by cooling )
power-limited
These are transparent planning estimates, not a quote. A real build needs a proper feasibility study — that’s where we help. Open the calculator →